Water Treatment Plant Pump Station Upgrade
The current pump station serving Springfield's service area is approaching 30 years of age. The city plans to build a new pump station to replace the outdated system. This new facility will feature cutting-edge technology, ensuring a more efficient and dependable service.
Project Status:
Workers are currently forming and pouring the concrete foundation for the new one-million-gallon underground storage tank.
Project Manager:
Kim Eakes, P.E., Griggs and Maloney, Inc.
Start: November 29, 2023
Estimated completion: September 2025 (Estimated)
Estimated Cost: $10,640,000
Funding Source: Local Funding
Contractor: J. Cumby Construction, Inc.
Engineering Firm: Griggs and Maloney, Inc.