2024 City Sidewalk Project:
This project includes the installation of approximately 1600 linear feet of sidewalk along the north side of Mooreland Drive.
Project Status:
- Mooreland Drive Installation
- Workers are currently installing the drainage system needed for the project.
Project Manager:
Clayton Moore
Start: May 2024
Estimated completion: June 2024 (Estimated)
Estimated Cost: $678,459
Funding Source: The City of Springfield
Contractor: L & G Construction Company