To request an inspection contact the Community Development & Planning Department at (615) 382-2200. A city inspector will inspect the property within 3 business days. A tag will be left on the property informing whether the property passed or failed.
HVAC Inspections
The City of Springfield requires a rough-in and final inspection. Contact the Community Development & Planning Department at (615) 382-2200.
Gas Inspections
The City of Springfield requires that a pipe house with proper pipe size including a stub sticking out of the house at the meter. After completion of installation, the contractor will be required to air test the line at a minimum of 30 PSI for at least 24 hours. While the pipe is under pressure test you may call city hall to request a codes enforcer to inspect the installation of the gas pipe line. If the pipe passes inspection, an order will be placed to have a customer service representative install the gas meter and establish service.
New Construction Building Permit
The City of Springfield requires a footing, framing, and final inspection on all new construction. Contact the Community Development & Planning Department at (615) 382-2200 to schedule these inspections.
- Prior to the framing inspection property must have passed rough in plumbing and electrical inspections.
- Prior to the final inspection property must have passed final plumbing and electrical inspections.